Summary of all Projects that will be addressed with our Bond Funds:
New Elementary School Project:
Budget: $15.1 million
- In Design Development phase of architecture
- Will interview the three finalists for the General Contractor/Construction Manager this week (selection recommendation for board vote on April 11
- Currently bidding out the Utility Extension work
Flathead High School:
Budget: $18.2 million
- Morrison-Maierle/LPW have begun meeting with representatives from
Flathead High School and the school district to start the preliminary programming and schematic design of the new construction, which will incorporate a new gym, locker room, classrooms, flexible learning spaces (21st Century Learning) and deferred maintenance.
Linderman Education Center, Agricultural Education Center and the Five Elementary Schools
(Elrod, Edgerton, Hedges, Peterson & Russell):
- Currently soliciting a Request for Proposal for Architectural/Engineering services for these projects.
Here are the details for the school projects:
Edgerton School located at 1400 Whitefish Stage, Kalispell, MT 59901:
Budget: $1,236,600
- Create additional flexible learning spaces in the area above the Library
- Perform deferred maintenance tasks including security systems
Elrod School located at 412 3rd Ave W, Kalispell, MT 59901:
Budget: $2,616,000
- ? Build new regulation sized gymnasium
- Convert existing gymnasium to small group teaching spaces – it will retain its use as a
Elrod Cafeteria
- Create additional flexible learning spaces
- Perform deferred maintenance tasks including security systems
Hedges School located at 827 4th Ave E, Kalispell, MT 59901:
Budget: $1,871,600
- Build new Multi-purpose space for Cafeteria and Learning
- Convert existing Cafeteria space to small group teaching spaces
- Remodel interior areas for flexible multi-use learning spaces
- Perform deferred maintenance tasks including security systems
Peterson School located at 1119 2nd St W, Kalispell, MT 59901:
Budget: $1,868,000
- Build new regulation sized gymnasium
- Convert existing gymnasium to small group teaching spaces
- Create additional flexible learning spaces
- Perform deferred maintenance tasks including security systems
Russell School located at 227 W Nevada St, Kalispell, MT 59901:
Budget: $2,092,000
- Build new regulation sized gymnasium
- Convert existing gymnasium to small group teaching space
- Create Music Room
- Create additional flexible learning spaces
- Perform deferred maintenance tasks including security systems
Linderman Education Center:
Budget: $3.4 million
- Remodel entire facility including commons, dining area and science lab
- Deferred maintenance; including security systems
H.E. Robinson Ag Center:
Budget: $4.6 million
- New 4 classrooms
- New office area
- New info commons area
- New science laboratory
- New welding shop
- Additional general shop and storage area
- Remodel toilet and locker areas
- Remodel interior area for 2 new classrooms
- Addition and remodel animal care facility
- New Roof
- Security