April 4, 2017: Summary of all Projects With Detail

Summary of all Projects that will be addressed with our Bond Funds:

New Elementary School Project:

Budget: $15.1 million

  • In Design Development phase of architecture
  • Will interview the three finalists for the General Contractor/Construction Manager this week (selection recommendation for board vote on April 11
  • Currently bidding out the Utility Extension work

Flathead High School:

Budget: $18.2 million

  • Morrison-Maierle/LPW have begun meeting with representatives from

Flathead High School and the school district to start the preliminary programming and schematic design of the new construction, which will incorporate a new gym, locker room, classrooms, flexible learning spaces (21st  Century Learning) and deferred maintenance.

 Linderman Education Center, Agricultural Education Center and the Five Elementary Schools

(Elrod, Edgerton, Hedges, Peterson & Russell):

  • Currently soliciting a Request for Proposal for Architectural/Engineering services for these projects.

Here are the details for the school projects:

Edgerton School located at 1400 Whitefish Stage, Kalispell, MT 59901:

Budget: $1,236,600

  • Create additional flexible learning spaces in the area above the Library
  • Perform deferred maintenance tasks including security systems

Elrod School located at 412 3rd Ave W, Kalispell, MT 59901:

Budget: $2,616,000

  • ? Build new regulation sized gymnasium
  • Convert existing gymnasium to small group teaching spaces – it will retain its use as a

Elrod Cafeteria

  • Create additional flexible learning spaces
  • Perform deferred maintenance tasks including security systems

Hedges School located at 827 4th Ave E, Kalispell, MT 59901:

Budget: $1,871,600

  • Build new Multi-purpose space for Cafeteria and Learning
  • Convert existing Cafeteria space to small group teaching spaces
  • Remodel interior areas for flexible multi-use learning spaces
  • Perform deferred maintenance tasks including security systems

Peterson School located at 1119 2nd St W, Kalispell, MT 59901:

Budget: $1,868,000

  • Build new regulation sized gymnasium
  • Convert existing gymnasium to small group teaching spaces
  • Create additional flexible learning spaces
  • Perform deferred maintenance tasks including security systems

Russell School located at 227 W Nevada St, Kalispell, MT 59901:

Budget: $2,092,000

  • Build new regulation sized gymnasium
  • Convert existing gymnasium to small group teaching space
  • Create Music Room
  • Create additional flexible learning spaces
  • Perform deferred maintenance tasks including security systems

Linderman Education Center:

Budget: $3.4 million

  • Remodel entire facility including commons, dining area and science lab
  • Deferred maintenance; including security systems

H.E. Robinson Ag Center:

Budget: $4.6 million

  • New 4 classrooms
  • New office area
  • New info commons area
  • New science laboratory
  • New welding shop
  • Additional general shop and storage area
  • Remodel toilet and locker areas
  • Remodel interior area for 2 new classrooms
  • Addition and remodel animal care facility
  • New Roof
  • Security